CMRL to procure additional TBMs as tunnelling work faces delays in Phase II network
international

CMRL to procure additional TBMs as tunnelling work faces delays in Phase II network

The Hindu · May 13, 2026, 7:29 PM

Why this matters: an international story with cross-border implications worth tracking.

Officials attribute the delay to cancellation of tenders for constructing stations and shifting utility pipelines; of the 69.05 km of tunnelling work to be done, only 28.11 km has been completed

Read full story on The Hindu → More top stories